Addis Ababa, Asmara, Massawa 1992
Feasibility study for a broadcasting project
The Eritrea National Television had the objective to expand its coverage to
90% of the country. Its Asmara transmitters (1000 watts) and Assab (500 watts)
did not provide service to the towns of Massawa, Keren, Tesseney, Barentu and
Akordat. YRH and a Canadian partner were mandated to conduct a feasibility study
to improve on the existing network.
Studies based on topographical maps and a field survey allowed us to propose a national network that included:
|
Asmara Site | |
|